光伏发电系统非计划孤岛问题的研究
CSTR:
作者:
作者单位:

(1.国网安徽省电力有限公司,安徽 合肥 230061;2.电力设备电气绝缘国家重点实验室(西安交通大学),陕西 西安 710049;3.北京中恒博瑞数字电力科技有限公司,北京 100085;4.西安交通大学电气工程学院, 陕西 西安 710049)

作者简介:

王同文(1981—),男,博士,高级工程师,研究方向为电力系统继电保护技术;E-mail:shqzuser@163.com
徐靖东(1983—),男,硕士,高级工程师,研究方向为新能源的控制与保护。E-mail:xjd_xjtu@xjtu.edu.cn

通讯作者:

中图分类号:

基金项目:

国家重点研发计划资助(2017YFB0902900);国网安徽省电力有限公司科技项目资助(52120017001G)


Research on non-scheduled islanding supplied by photovoltaic power generations
Author:
Affiliation:

(1. State Grid Anhui Electric Power Co., Ltd., Hefei 230061, China;2. State Key Laboratory of Electrical Insulation for Power Equipment (Xi’an Jiaotong University), Xi’an 710049, China;3. Beijing Join Bright Digital Power Technology CO., LTD., Beijing 100085, China;4. School of Electrical Engineering, Xi’an Jiaotong University, Xi’an 710049, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    被动式反孤岛保护在现场应用广泛,但存在较大的动作死区,无法完全区分孤岛效应与暂态电压跌落,因此反孤岛保护无法与光伏的低电压穿越控制形成有效的配合。针对一起配电网孤岛案例,分析了孤岛产生的机理,对基于电压和频率检测的被动式反孤岛保护的适用性进行了评估。通过建立基于PSCAD的光伏孤岛仿真模型,分析了从故障发生到孤岛产生的过程中电压和频率的暂态特性,揭示了现场保护动作特性与孤岛效应的关系,给出了基于传统配电网的保护应对建议。

    Abstract:

    Passive anti-islanding protections have been widely used in field, but all of them have dead zone of protection operation. On this account, islanding effect cannot completely be distinguished from transient voltage sags. Therefore, the anti-islanding protection cannot effectively cooperate with the low voltage traversing control of photovoltaics. In this paper, the mechanism of islanding is analyzed, and the applicability of passive anti-islanding protections based on voltage and frequency detection is evaluated. The transient characteristics of voltage and frequency during the process from fault to islanding are analyzed by establishing a PSCAD-based photovoltaic islanding simulation model. The relationship between the operation characteristics of field protection and islanding effect is revealed, and the protection countermeasures based on traditional distribution network are proposed. This work is supported by National Key Research and Development Program of China (No. 2017YFB0902900) and Science and Technology Project of State Grid Anhui Electric Power Co., Ltd. (No. 52120017001G).

    参考文献
    相似文献
    引证文献
引用本文

王同文,徐靖东,邵庆祝,等.光伏发电系统非计划孤岛问题的研究[J].电力系统保护与控制,2020,48(5):173-180.[WANG Tongwen, XU Jingdong, SHAO Qingzhu, et al. Research on non-scheduled islanding supplied by photovoltaic power generations[J]. Power System Protection and Control,2020,V48(5):173-180]

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2019-04-18
  • 最后修改日期:2019-06-13
  • 录用日期:
  • 在线发布日期: 2020-03-15
  • 出版日期:
文章二维码