考虑直接负荷控制与风电不确定性的输电网扩展规划
CSTR:
作者:
作者单位:

(1.国网湖北省电力有限公司,湖北 武汉 430077;2.水火电资源优化配置与仿真技术实验室(国网湖北省电力 有限公司经济技术研究院),湖北 武汉 430077;3.强电磁工程与新技术国家重点实验室,电力安全与 高效湖北省重点实验室(华中科技大学电气与电子工程学院),湖北 武汉 430074)

作者简介:

蒋 霖(1963—),男,教授级高级工程师,研究方向为电网规划及能源发展战略;
郑倩薇(1994—),女,通信作者,硕士研究生,研究方向为可再生能源并网,输电网规划等。E-mail:qianwei_zheng@ hust.edu.cn

通讯作者:

中图分类号:

基金项目:

中国博士后科学基金项目资助(M2018642841); 国家自然科学基金项目资助(51707070); 国网湖北省电力有限公司科学技术项目资助“大型枢纽电网主配网协调规划技术研究”


Transmission network expansion planning considering direct load control and wind power uncertainty
Author:
Affiliation:

(1. State Grid Hubei Electrical Power Co., Ltd., Wuhan 430077, China;2. Hydrothermal Power Resource Optimization and Simulation Laboratory (State Grid Hubei Electrical Power Co., Ltd. Economics Research Institute), Wuhan 430077, China;3. State Key Laboratory of Advanced Electromagnetic Engineering and Technology, Hubei Electric Power Security and High Efficiency Key Laboratory (School of Electrical and Electronic Engineering, Huazhong University of Science and Technology), Wuhan 430074, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    需求响应项目的推广以及风电并网后电源侧出力的不确定性,给电力系统的输电网规划带来了新的机遇和挑战。为利用需求响应减少建线投资,建立了考虑直接负荷控制参与N-1预想故障潮流调整的输电网规划模型。采用基于历史数据凸包顶点的极限场景法处理风电不确定性,保证所建立的输电网规划模型为易于求解的混合整数规划问题。结合实际工程参数,基于改进的IEEE24节点系统进行仿真。仿真结果体现了直接负荷控制在缓解潮流越限、减少建线成本方面的作用,说明需求响应措施在保证系统运行安全性的前提下能够提高规划经济性,通过调整凸包范围能够有效调节所提模型的经济性与鲁棒性。

    Abstract:

    The promotion of demand response programs and the uncertainty caused by wind power integration create opportunity and challenge to transmission network expansion planning. To defer the transmission line investment with demand response, the transmission expansion planning model is proposed considering direct load control in generation re-dispatch for N-1 contingency. The extreme scenario method based on the convex hull vertices of history data is utilized to tackle with wind power uncertainty, which ensures the proposed model is a solvable mixed integer linear programming model. The modified IEEE 24-node system is tested with practical parameters. The function of demand response in relieving power flow overload and reducing transmission line investment is presented in the simulation results, which indicates demand response can improve the economy of power grid planning with the guarantee of system operation security. By adjusting the range of convex hull, the balance between economy and robustness of the proposed model can be reached. This work is supported by China Postdoctoral Scientific Fund (No. M2018642841), National Natural Science Foundation of China (No. 51707070), and Science and Technology Project of State Grid Hubei Electric Power Co., Ltd. “Technical Research on Large Hub Power Grid Active Distribution Network Coordination Planning”.

    参考文献
    相似文献
    引证文献
引用本文

蒋霖,郑倩薇,王枫,等.考虑直接负荷控制与风电不确定性的输电网扩展规划[J].电力系统保护与控制,2020,48(3):138-146.[JIANG Lin, ZHENG Qianwei, WANG Feng, et al. Transmission network expansion planning considering direct load control and wind power uncertainty[J]. Power System Protection and Control,2020,V48(3):138-146]

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2019-03-13
  • 最后修改日期:2019-04-28
  • 录用日期:
  • 在线发布日期: 2020-02-23
  • 出版日期:
文章二维码
关闭
关闭